| Rebuilding News |
|
|
|
|
May 2010
We are settling into our new common center. The kitchen, dining room,
JMT's office
Our new spacious, stainless steel kitchen!
Dining room
This is our beautiful view from the porch in Spring.
On April 10th, 2010 Bishop Anthony Taylor of Little Rock consecrated A simple, but beautiful building in the style of a Franciscan Mission, it uses been worshiping and sharing common meals, and ministry in a make shift Over 125 monastic community members and guests, including Bishop founder of the well respected humanitarian agency of Mercy Corps, and Phil
The celebration was joyful and awesome. The music was typically spirited with
The Brothers and Sisters of Charity is part of the New Monasticism Movement, John Michael Talbot
The belltower permacrete is complete and the ground is graded for the plaza. Southwest picture of the common center and chapel.
Chapter Room Ceiling with Cross Beams
Dining Room Fireplace Progress
Gift shop shelving at the entry near the porter's desk.
Cement plaza area poured.
Railing up dining room steps. January 27, 2010
We have the front chapel doors installed and the stone facing is done!
Chapel entry taken from inside the chapel. The room to the left is the
Close up of stone work and statue niche in front of the chapel.
The glass rail in front of the loft is installed.
The detailing for the belltower is being installed.
The stonework continues. It will wrap around the dining room porch.
Kitchen stove
Baking station range. The protective sheets covering the stainless Work has begun on the water feature for the interior cloister garden. January 16, 2010
View of interior back fo chapel. The vestry is on the right and the Detailing in chapel south wall. Chapel interior after permacrete and painting is complete. We hope to worship here soon and very soon! New dining room upper windows have been completed and will get a fresh
The doors and window are in and drywall in place in the new dining room.
cross on the roof. The bell will be hung in the belltower soon. The offices are almost all painted but there is much to be done inside, including the kitchen, bathrooms, etc. December 12, 2009
The railing for the chapel loft is complete. A glass panel will complete the rail.
The north side of the chapel has part of the roof up and the second coat
The front of the chapel has a full coat of permacrete.
The chapel interior is getting its styrofoam mouldings applied and coated
The chapter room is taking shape.
Interior walls.
The library allows lots of natural light because of the new skylights.
Pillars are added to the south side of the building outside the dining room.
Cloister walkway and roof are progressing nicely.
Fireplace between kitchen and dining room started.
Hearth installed.
Windows on the dining room fitted.
Styrofome embelishments around the door.
Chapel face gets its first coat of permacrete.
November 18, 2009
Wood for roof in place.
Porch view from front.
Top in place with tar paper.
Rock lining the cinderblock below the porch.
November 11, 2009 Roofing over dining room porch nearly ready to start.
Pillars with first coat of permacrete and decorative color in center.
Roofing insulation. A sheet of plywood followed by a layer of the pictured
Shot looking from the cloister walk towards the chapel.
The belltower cupola has been placed.
South side of the common center upper portion has received it's
The chapel loft is 3/4 done - this is a view of the loft ceiling.
Front of common center receives its first coat of permacrete.
Chapel interior ceiling is complete and the belltower sheeting is nearly done. November 6, 2009
Porch cover outside the dining room.
Front view of the porch cover over dining room.
The ceiling of the chapel is complete!
The styrofoam at the bottom of the pillar gets a coat of permacrete. November 5, 2009
Chapel ceiling - more than half done!
We had a freeze last night so the workers had to wait until later in
The south side of the chapel.
Moldings from styrofoam are fitted around the lower third of the pillars.
Closer view of column forms.
November 4, 2009
Chapel ceiling underway!
Interior view of chapel ceiling
Common center, looking from greenhouse area
First coat of permacrete is applied to the building and cinderblock.
Beginning for fireplace in dining room.
Front porch looking outward
Close up of permacrete. Styrofoam insulation is showing at the bottom October 28, 2009
The belltower is being fitted with sheeting.
The finishing touches are being put on the cupola. There is still a hole
The sheeting on the arches is nearly complete.
Beginning sheeting of the exterior of the library (behind cloister walk)
Upper support beam in the chapel is complete.
Stove hood arrived.
An exciting day at Little Portion. The Sky Trak (orange machine on left)
A crane lifts the truss up over the top of the chapel and sets it in place.
Next second truss being put into place (shown from inside the chapel).
Almost all trusses up into position.
All chapel trusses in place.
Sheeting for the cloister walk is nearly complete and the porches
The cloister walk ceiling taken at an intersection.
The dining room ceiling is complete. Note the upper windows to allow
Exterior shot of the dining room windows.
The east side of the building being prepared for permacrete.
The structure for the arches at the front of the building completed September 25, 2009 Arches being formed in the cloister walk ![]() Steps up to dining room poured ![]() Pine ceiling in dining room started September 23, 2009 ![]() Overhead view of chapel (foreground), dining room (upper right side) and cloister walk. ![]() Belltower is lifted up on a crane and set on it's pad. ![]() Chapel floor being poured ![]() Chapel view from belltower September 22, 2009 ![]() The stairs to the dining room are being poured tomorrow. The pyramid shaped item on the porch is the top of the bell tower which we hope will be placed tomorrow. September 21, 2009 We've been getting several inches of rain the last few weeks which slowed the progress on the exterior and exposed interior areas. Work is being done on the inner walls structure and electric wiring. ![]() Your can see the arches of the cloister walk taking shape. ![]() The pad for the belltower has been poured and is being prepared ![]() The chapel subfloor has been leveled and covered with plastic. ![]() The dining room rafters are set in place. ![]() A lot of progress has been made on the east end of the building. September 8, 2009 Today's shot taken on the Sky Trak. Scaffolding has been removed. Exterior from dining room towards chapel. Posts have been placed for the covered porch. ![]() The cloister walk is taking shape. August 31, 2009 Scaffolding coming down. Chapel interior (notice the cement pillars and windows at top. August 25, 2009 A member of the construction crew waves as we anxiously await the placement of the final block for the chapel front. ![]() The final block is placed. Thumbs up for the segment completed. August 22, 2009 Chapel and Common Center - northeast view Common Center - north view. Notice the branch at the top of the chapel peak. It is a tradition of construction workers to put a "tree" at the buildings highest peak. Common Center - western side Common Center - southern side August 18, 2009 Taken from the new dining room. Far left by ladder is the chapter room, left with scaffolding is the chapel, cloister garden is in the center, the classroom is direcdtly behind the garden, library and archives is on one side of the cloister garden and kitchen is to the right. ![]() Pantry and kitchen in foreground, wellness rooms, and offices in rear. ![]() Chapel is growing higher! ![]() Cloister walk with library in the rear. The dining room cement floor has been poured. ![]() The new dining room will overlook the prayer garden. ![]() Interior view taken from the chapter room. ![]() Overview of monastery from northwest angle. August 12, 2009 Trusses over the office area are lifted by a large TeRex. Each truss is maneuvered into place. The rear is JMT's office. Truss nearly set. This area is the wellness rooms. ![]() Interior work continues: wall struts are set in place. ![]() CHAPEL SHOWN FROM FRONT - NOTE THE NICHES PLACED FOR STATUES. ![]() CLOSE UP OF CHAPEL INNER AND OUTER WALLS AUGUST 7, 2009: CHAPEL NORTH SIDE WALLS AND FRONT STARTED CLOSE UP OF CHAPEL'S INNER WALLS (right)
|